Project Management 知到智慧树答案2024 z27050
第一章 单元测试
1、
The main objectives of project management are ( )
A:Calendar dates, facilities available, funding
B:Profitability, cost, time
C:Customer satisfaction, cost, time
D:Time, cost, quality, and/or scope
答案: Time, cost, quality, and/or scope
2、
The person responsible for balance the time, cost and quality objectives to achieve project success is ( )
A:The line manager
B:The Human Resources Department
C:The project manager
D:The executive sponsor
答案: The project manager
3、
The knowledge areas in PMBOK include: ( )
A:Cost management
B:Scope management
C:Risk management
D:Information management
答案: Cost management ,Scope management,Risk management
4、
The temporary nature of projects means that a project has a short duration. ( )
A:错
B:对
答案: 错
5、
There are five process groups in PMBOK.( )
A:错
B:对
答案: 对
第二章 单元测试
1、
In which organization structure would the project manager is fully responsible for the project ( )
A:Projectized
B:Weak matrix
C:Functional
D:Strong matrix
答案: Projectized
2、
In which type of matrix structure would a project manager most likely have a command of technology ( )
A:Cross-cultural matrix
B:Strong matrix
C:Weak matrix
D:Balanced matrix
答案: Strong matrix
3、
Which of the following items are the roles of a project manager ( )
A:Project manager is a facilitator in terms of responsibilities to determine tasks, deadlines, and required resources
B:Project manager should be an expert in a particular area
C:Project manager should be a generalist
D:Project manager should own comprehensive ability to solve problems
答案: Project manager is a facilitator in terms of responsibilities to determine tasks, deadlines, and required resources,Project manager should be a generalist,Project manager should own comprehensive ability to solve problems
4、
Project team member probably may lose his or her job in matrix organizational form if the project gets cancelled. ( )
A:对
B:错
答案: 错
5、
Generally, project manager is the soul of project team. ( )
A:对
B:错
答案: 对
第三章 单元测试
1、
The document that officially sanctions the project is the ( )
A:Project plan
B:Benefit/Cost analysis
C:Project charter
D:Feasibility study
答案: Project charter
2、
Commonly, Work Breakdown Structure can be constructed as ( )
A:Baseline
B:Tree diagram
C:Analysis table
D:Dictionary
答案: Tree diagram
3、
Project initiation is approved for the following main reasons ( )
A:Technological advance
B:Market demand
C:Executive requirement
D:Customer request
答案: Technological advance,Market demand ,Customer request
4、
Project scope can influence the time, quality and cost of the project. ( )
A:错
B:对
答案: 对
5、
Work Package is in the managerial level of the WBS.( )
A:对
B:错
答案: 错
下方是付费阅读内容:本平台商品均为虚拟商品,无法用作二次销售,不支持退换货,请在购买前确认您需要购买的资料准确无误后再购买,望知悉!
完整答案需点击上方按钮支付5元购买,所有答案均为章节测试答案,无期末答案。购买后上方矩形框将出现已付费的隐藏内容。
点关注,不迷路,微信扫一扫下方二维码
关注我们的公众号:阿布查查 随时查看答案,网课轻松过
为了方便下次阅读,建议在浏览器添加书签收藏本网页
电脑浏览器添加/查看书签方法
1.按键盘的ctrl键+D键,收藏本页面
2.下次如何查看收藏的网页?
点击浏览器右上角-【工具】或者【收藏夹】查看收藏的网页
手机浏览器添加/查看书签方法
一、百度APP添加/查看书签方法
1.点击底部五角星收藏本网页
2.下次如何查看收藏的网页?
点击右上角【┇】-再点击【收藏中心】查看
二、其他手机浏览器添加/查看书签方法
1.点击【设置】-【添加书签】收藏本网页
2.下次如何查看收藏的网页?
点击【设置】-【书签/历史】查看收藏的网页